C&S FRIEGHT DEPOT – HISTORICAL RENOVATION & SITE IMPROVEMENTS
Fort Collins, CO

OWNER: City of Fort Collins
P.O. Box 580
Fort Collins, CO 80524
   
PROJECT SCHEDULE:   Design Start Date:             N/A
Construction Start Date:     January, 2001
Original Completion Date:   August, 2001
Actual Completion Date:     September, 2001
   
PROJECT BUDGET: Contract Award Amount:     $ 1,869,600
Final Construction Amount: $ 1,964,994


The City of Fort Collins envisioned the Colorado and Southern Railroad Station of yesteryear as a new northern terminal for the Transportation System (Transfort) in Fort Collins. The design is in keeping with the historical flavor of the existing structure with updated offices, parking, and shelters. The site of this particular project is of major consequence in that it required extensive demolition, engineering and subgrade work in order to prepare for shelters featuring colored and patterned concrete, masonry pavers, concrete paving and landscaping.