FORT CARSON ARMY MOBILIZATION WAREHOUSE
Fort Carson, CO

OWNER: Army Corps of Engineers
Resident Engineer
P.O. Box 13049
Fort Carson, CO 80914
   
PROJECT SCHEDULE:   Design Start Date:             By Corps of Engineers
                                        (no date available)
Construction Start Date:     October, 2000
Original Completion Date:   August, 2001
Actual Completion Date:     November, 2001
   
PROJECT BUDGET: Contract Award Amount:     $3,888,800
Final Construction Amount: $3,950,000
   
  “…MBI’s project management style is decisive, collaborative, and cooperative, ingredients I would hope for on a design-build project…”
-John A. Hetager, P.E., COE


This project for the U.S. Army involved extensive pre-construction utility and grade work to bring the site to a ready position for foundation excavation. As with all Corps of Engineer work the quality control and documentation portions of the project are significant and are in excellent order for the project. The building is unique in that masonry walls were incorporated with a pre-engineered building with a composite roof deck. The interior has high-rise freestanding storage racks and two-story office area.