HIGHLINE MOTORS – LATE MODEL AUTO DEALERSHIP
Fort Collins, CO

OWNER: Peppe De Marco
4321 South Mason
Fort Collins, CO 80525
   
PROJECT SCHEDULE:   Design Start Date:             February, 2000
Construction Start Date:     July, 2000
Original Completion Date:   November, 2000
Actual Completion Date:     November, 2000
   
PROJECT BUDGET: Contract Award Amount:     $411,438.00
Final Construction Amount: $411,438.00
   
 

“ Everything, down to the littlest detail, was completed within budget and on time.” - Peppe DeMarco



The Highline Motors project was built in essentially two phases. The first phase was comprised of a double modular semi permanent office building and parking lot which was the essence of the Highline Motors operation during its’ start up and initial growth period. During that period Highline Motors raised capitol and worked with MBI and the City of Fort Collins in order to Design/Build the permanent facility shown in the picture. The facility also contains an attached automobile maintenance area.