SANDSTONE RANCH ATHLETIC FIELDS
Longmont, Colorado

OWNER: City of Longmont
Community Development Dept.
747 Coffman Street
Longmont, CO 80501
   
PROJECT SCHEDULE:   Design Start Date:             January 2000
Construction Start Date:     March 2000
Original Completion Date:   December 2000
Actual Completion Date:     May 2001
   
PROJECT BUDGET: Contract Award Amount:     $ 5,602,218
Final Construction Amount: $ 5,914,684
   
  “I am more than pleased with your performance. You are doing a superb job” – Paula Fitzgerald


This project was bid in 1999, and awarded in March of 2000. The project involves 4 athletic fields, support facilities and other structures over a 100-acre site. The start date was delayed due to the governmental approval process. Delays due to underground conditions and addition of changes to the work, changed the overall construction time. In spite of many obstacles and cost over-runs, MBI completed the project to the City’s satisfaction..